Your cart is currently empty!


Data Center Construction – Huawei Office, Al Gassar Tower
Client: Huawei Technologies – Qatar
Location: Al Gassar Tower, Doha, Qatar
Project Type: Turnkey ELV & Data Center Infrastructure
Duration: 3 months
Status: Successfully Completed
🏗️ Scope of Work
ELV Techies Integrators LLC was selected to execute the end-to-end construction and commissioning of a compact, high-efficiency data center for Huawei’s Qatar headquarters located in the prestigious Al Gassar Tower. The project involved critical coordination with building management, Huawei’s IT consultants, and international compliance standards.
⚙️ Key Deliverables
Server Room Design & Layout
- Rack placement, airflow management, and physical security
- Raised flooring and ceiling cable tray systems
Structured Cabling & Fiber Backbone
- CAT6A UTP cable installations with patch panels
- Multi-core fiber optic cabling with splicing and testing
- Complete cable labeling and documentation
Rack & Equipment Installation
- Data racks with grounding and power cabling
- Patch panels, vertical/horizontal cable managers
- Device mounting (firewalls, routers, switches)
Power & Cooling Infrastructure
- UPS systems with redundancy
- Precision air conditioning coordination
- Power distribution units (PDUs) and load balancing
Access Control & CCTV Security
- Biometric access control for restricted zones
- IP CCTV cameras with local NVR storage
- Access event logging and remote monitoring setup
Testing & Commissioning
- Complete end-to-end testing and validation
- Handover documentation and operational training
✅ Challenges Overcome
Coordinated with tight office working hours and minimal disruption
Delivered precise documentation and labeling per Huawei global standards
Managed international compliance for structured cabling and fire systems
Project Snaps
